Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E, PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 23/0152, UPIN 19101MF0XY01
Vendor/Entity Legal Name (if applicable): Conrad Construction Co., Ltd.
MWDBE Contracted Goal (if applicable): 21%
MWDBE Current Participation (if applicable): 0%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Conrad Construction Co., Ltd. in connection with Anderson Road - Hiram Clarke Road to Almeda Road - 2018, adding 11 calendar days, with an addition in the amount of $169,395.00, Job No. 23/0152-2, UPIN 19101MF0XY01, Precinct 1, MWDBE Contracted Goal: 21%, MWDBE Current Participation: 0%.
end
Background and Discussion:
Project includes completion of the two-lane concrete curb and gutter road with sidewalk on both sides and left turn lanes at the intersections approximately 7,800 linear feet of Anderson Road construction from 500 feet west of Hiram Clarke Road to Almeda Road/FM 521 (Segment 2).
This change in contracts includes:
The increasing of proposed temporary driveway quantity by 38 each. Total on the project is 48 there are only 10 in the bid quantity. ($48,500)
Item #38 - Structural Concrete (wingwall) - Increase quantity by 30 cy to construct proposed wingwalls per plans. Bid quantity is short of required amount. ($55,500.00)
Item #158 - Install temporary Conflict Manhole - Add new line item to construct conflict manhole around 6" steel water line to avoid delay in project. ($18,980.00 - 4 Days)
Item #160 - Adjust Manhole Tops - Add new line item to adjust existing manhole tops in conflict with proposed pavement elevations. ($13,290 - 2 days)
Item #48 - Precast Concrete Standard Manhole - Increase existing line item by 1 each to avoid conflict with ...
Click here for full text