Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 22/0461, UPIN 19101MF0XV01
Vendor/Entity Legal Name (if applicable): Allgood Construction Co., Inc.
MWDBE Contracted Goal (if applicable): 25%
MWDBE Current Participation (if applicable): 35.56%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Allgood Construction Co., Inc., in connection with West Gulf Bank Road from I45 to Airline Drive, adding five calendar days, with an addition in the amount of $9,831.73, Job No. 22/0461-4, UPIN 19101MF0XV01, Precinct 2, MWDBE Contracted Goal: 25%, MWDBE Current Participation: 35.56%.
end
Background and Discussion:
This project includes the construction of four 11-foot-wide concrete pavement with a 24-foot median, and 8-foot-wide sidewalk along both sides West Gulf Bank Road from Interstate 45 Freeway to Airline Drive. It also includes the drainage improvements.
The change order includes the following:
- Driveway 10-6 at STA 144+75 RT has a grade mismatch with the car wash pavement. To resolve this, remove all concrete on the west side of the driveway down to the Right of Way, and regrade the entire area including the sidewalk and driveway to meet Harris County's maximum grade. This change will add $2,239.28 and additional 1 day to the contract.
- At Station 109+52, an existing sanitary sewer cleanout conflicts with the proposed storm sewer installation. To resolve this issue, the cleanout should be removed and replaced, relocating it to the right-of-way boundary to ensure it is clear of the proposed storm sewer. This change will add $2,903.25 and additional of 1 day to the contract.
- The traffic control plan at the Airline and West Gulf Bank in...