Legislation Details

File #: 24-4682    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 7/24/2024 In control: Commissioners Court
On agenda: 8/6/2024 Final action: 8/6/2024
Title: Request for approval of a change in contract with SER Construction Partners, LLC, in connection with Crosby Lynchburg Road Phase 3, with an addition in the amount of $39,317.60, Job No. 21/0059-9, UPIN 17102MF0MV01, Precincts 2 & 3, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer
Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 21/0059, UPIN 17102MF0MV01
Vendor/Entity Legal Name (if applicable): SER Construction Partners, LLC

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with SER Construction Partners, LLC, in connection with Crosby Lynchburg Road Phase 3, with an addition in the amount of $39,317.60, Job No. 21/0059-9, UPIN 17102MF0MV01, Precincts 2 & 3, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
end

Background and Discussion:
Project includes the reconstruction of approximately 1.85 miles of Crosby Lynchburg Road (FM 2100) from Magnolia Drive south to Lochness Drive and includes the widening of the bridge over HCFCD Channel G103-05.

Change includes:
- Per field condition, remove the previously installed TY E Inlet at Sta. 100+76 (Sheet 93), extend the 24-IN RCP by 95 LF to the South, and reinstall and convert the inlet to a MOD TY A inlet in the CL 3 limits. $19,909.74 - 0 days
- There are existing utility poles with unstable condition and unclaimed which need to be removed. $10,381.49 - 0 days.
- Per field condition, Convert the existing TY E Inlet at Sta. 50+63 LT (CL 3 Limits) to a storm manhole, extend 8 LF of 24-IN RCP and add 1 - 24" SET on the project. $4,325.23 - 0 days.
- Offsite drainage swale that has been blocked by finish grading. After the re-evaluation and to eliminate the standing water in this area, it was determined that the offsite drainage needs to be connected to storm system. $10,353.84 - 0 days.
- The appro...