Legislation Details

File #: 24-4670    Version: 1 Name:
Type: Negotiation Status: Passed
File created: 7/24/2024 In control: Commissioners Court
On agenda: 8/6/2024 Final action: 8/6/2024
Title: Request for approval to negotiate with TEDSI Infrastructure Group, Inc., for professional engineering services of design, survey, and construction related services in connection with Traffic Signal - Brittmoore Road at Brittmoore Park Drive - FY23-24, UPIN 24035MF3GY01, Precinct 3.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Negotiation

Project ID (if applicable): 24035MF3GY01
Vendor/Entity Legal Name (if applicable): TEDSI Infrastructure Group, Inc.

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Request Summary (Agenda Caption):
title
Request for approval to negotiate with TEDSI Infrastructure Group, Inc., for professional engineering services of design, survey, and construction related services in connection with Traffic Signal - Brittmoore Road at Brittmoore Park Drive - FY23-24, UPIN 24035MF3GY01, Precinct 3.
end

Background and Discussion:
Traffic signals are installed to improve the operation of an intersection and better facilitate pedestrian activities. As such, the consultant will be tasked with the signal design of the intersection to improve operations. The consultant will be tasked with evaluating pedestrian accessibility through the provision of crosswalks and associated median nose opening adjustments required to facilitate pedestrian activities.

Expected Impact:
Designing and constructing a traffic signal at this intersection will improve operations and better facilitate pedestrian activities.

Alternative Options:
This location currently operates as a minor street stop-controlled intersection. An alternative is to not signalize the intersection, which will not provide operational and pedestrian benefits.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken




Location:
Address (if applicable): Brittmoore Road at Brittmoore Park Drive
Precinct(s): Precinct 3