Legislation Details

File #: 24-4561    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 7/21/2024 In control: Commissioners Court
On agenda: 8/6/2024 Final action: 8/6/2024
Title: Request for approval of a change in contract with Centennial Contractors Enterprises, Inc., in connection with the HCCO Civil Courthouse Level 3, 6, & 7 Renovation - 2022, adding 90 calendar days, with an addition in the amount of $40,951.51, Job No. 22/0454-2, UPIN 23515MF2N801, Precinct 1, MWDBE Contracted Goal: 18.3%, MWDBE Current Participation: 44%.
Sponsors: Mony Hossain
Department: County Engineer
Department Head/Elected Official: Dr. Milton Rahman, Ph.D, P.E, PMP, CFM, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): 22/0454
Vendor/Entity Legal Name (if applicable): Centennial Contractors Enterprises, Inc.

MWDBE Contracted Goal (if applicable): 18.3%
MWDBE Current Participation (if applicable): 44%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Centennial Contractors Enterprises, Inc., in connection with the HCCO Civil Courthouse Level 3, 6, & 7 Renovation - 2022, adding 90 calendar days, with an addition in the amount of $40,951.51, Job No. 22/0454-2, UPIN 23515MF2N801, Precinct 1, MWDBE Contracted Goal: 18.3%, MWDBE Current Participation: 44%.
end

Background and Discussion:
The HCCO Civil Courthouse Level 3, 6, & 7 Renovation involves a partial renovation of three floors of the Harris County Civil Courthouse. Updates involve new floorplan layouts in the form of building out new offices, storage rooms, communications studio, open work areas, & a new break room. The goal of these changes is to further optimize the use of space on these floors for the benefit of the Office of the County Clerk.

This change in contract includes incidental added costs for added electrical, plumbing, and millwork scope/revisions on floors 3 & 6 brought about from existing field conditions or Owner requests. It also includes added contract calendar days to incorporate this added scope into the construction schedule.

Expected Impact:
These changes allow the contractor to bill for required changes resulting from unforeseen conditions and Owner Requests.

Alternative Options:
Should we not move forward with this change in contract, these items will remain unreconciled delaying the closeout of the contract and project.


Alignment with Goa...