Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Transmittal
Project ID (if applicable): UPIN 21289MF21501 - Job. No. 22/0444
Vendor/Entity Legal Name (if applicable): Mar-Con Services, LLC
MWDBE Contracted Goal (if applicable): 26%
MWDBE Current Participation (if applicable): 100%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Transmittal by the Office of the County Engineer of a substantial completion certificate with Mar-Con Services, LLC for improvements in connection with Emerald Forest Subdivisions Road and Drainage Improvements (Cypress Place-Ph II), Job No. 22/0444, UPIN 21289MF21501, Precinct 3, MWDBE Contracted Goal: 26%, MWDBE Current Participation: 100%.
end
Background and Discussion:
The Substantial Completion Certificate provides documentation that a capital improvement project meets the qualifications of Substantial Completion in accordance with the Contract Documents as determined by the County Engineer. Substantial Completion establishes the date on which a capital improvement enters service as a Harris County asset. The establishment and reporting of this date are important for all governmental entities as outlined in the GASB Statement #34, Capital Assets & Depreciation Guidance, August 31, 2001. These certificates provide a method by which Harris County may document and record this date.
Expected Impact:
N/A
Alternative Options:
N/A
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
X Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date
Agenda Item #
Action Taken
02/21/2023
23-0902
Contract Award - Mar-Con Services, LLC
04/23/2024
24/2182
Contract Amendment - 22/0444-1
Location: Emerald Forest Subdivisions Road and Drai...