Legislation Details

File #: 24-4538    Version: 1 Name:
Type: Public Necessity Status: Passed
File created: 7/19/2024 In control: Commissioners Court
On agenda: 8/6/2024 Final action: 8/6/2024
Title: Request for approval of a certain project, decreeing the project to be a public necessity and convenience, and directing the Harris County Real Property Division to acquire two (2) fee simple tracts for the public project known as Shaw Road Segment 2 - from south of Westlake Run Blvd to Boudreaux Rd - 2019, for the purpose of roadway construction, UPIN 20104MF1BU01, Precinct 3.
Sponsors: Mony Hossain
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Public Necessity

Project ID (if applicable): 20104MF1BU01
Vendor/Entity Legal Name (if applicable): Not applicable

MWDBE Contracted Goal (if applicable): Not applicable
MWDBE Current Participation (if applicable): Not applicable
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Request Summary (Agenda Caption):
title
Request for approval of a certain project, decreeing the project to be a public necessity and convenience, and directing the Harris County Real Property Division to acquire two (2) fee simple tracts for the public project known as Shaw Road Segment 2 - from south of Westlake Run Blvd to Boudreaux Rd - 2019, for the purpose of roadway construction, UPIN 20104MF1BU01, Precinct 3.
end

Background and Discussion:
This project consists of upgrading Shaw Rd from Northpointe Blvd. to Boudreaux Rd from partially half blvd, partially two lane asphalt to four lane concrete with curb and gutter 32' median within 100' of ROW with the following traffic signals: Sunset Canyon Dr. There is one outfall with inline detention and pond that will outfall to the Northpointe WCID detention system. The acquisition of the two parcels in this request are for the detention pond included in the improvements of this project.

Expected Impact:
The approval of this request will ensure the completion of the project Shaw Road Segment 2 - from south of Westlake Run Blvd to Boudreaux Rd - 2019.

Alternative Options:
If this request is not approved, it will cause delay in the completion of the project Shaw Road Segment 2 - from south of Westlake Run Blvd to Boudreaux Rd - 2019.




Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service

Prior Court A...