Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): 20104MF1BM01
Vendor/Entity Legal Name (if applicable): Arcadis, U.S., Inc.
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program
Request Summary (Agenda Caption):
title
Request for approval to execute an amendment with Arcadis, U.S., Inc. in the amount of $182,835.95 for professional engineering services to provide improvements to Grant Road Segment 4 - from Cypress Rose Hill Road to Telge Road - 2018, UPIN 20104MF1BM01, Precinct 3, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
end
Background and Discussion:
This amendment includes the addition of a USACE individual permit application which is required due to the preferred project outfall to Little Cypress Creek.
Expected Impact:
This amendment will allow the project storm drain outfall to be optimized to better fit the conditions.
Alternative Options:
An alternative would be to not optimize the storm drain outfall, resulting a less than desirable project.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
X Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date
Agenda Item #
Action Taken
4/9/2019
1.f.1
Authorization to Negotiate
5/19/2020
1.g.13
Agreement
Location: Grant Road
Address (if applicable): Grant Road
Precinct(s): Precinct 3
Fiscal and Personnel Summary
Service Name
Engineering
Current Fiscal Year Cost
Annual Fiscal Cost
Labor
Non-Labor
Total
Recurring Expenses
Funding Sources
Existing Budget
1070 - Mobility Fund
$
$182,835.95
$...