Legislation Details

File #: 24-4274    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 7/5/2024 In control: Commissioners Court
On agenda: 7/15/2024 Final action: 7/15/2024
Title: Request that the County Judge execute an amendment to an agreement with Flintco, LLC in the additional amount of $414,448 for additional heating, ventilation, air conditioning (HVAC) services for construction manager at risk for the construction of the 1111 Fannin Renovation Project for Harris County (220079).
Attachments: 1. 24-4274 Amendment Job No. 220079.pdf
Department: Purchasing
Department Head/Elected DeWight Dopslauf

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): 220079
Vendor/Entity Legal Name (if applicable): Flintco, LLC

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Request Summary (Agenda Caption):
title
Request that the County Judge execute an amendment to an agreement with Flintco, LLC in the additional amount of $414,448 for additional heating, ventilation, air conditioning (HVAC) services for construction manager at risk for the construction of the 1111 Fannin Renovation Project for Harris County (220079).
...end

Background and Discussion:
Harris County purchased 1111 Fannin to be the new offices for HCED, HCFCD, Purchasing, and HRRM. These four departments will occupy the majority of the building along with Harris County Public Health. This court amendment entails scope pertaining to the building's 1st Floor and HVAC system. This amendment entails added scope including HVAC changes, installation of new glass in 9 offices on the 11th floor, and removal & replacement of 3 Fan Powered Boxes


Expected Impact:
The Construction Manager At Risk will provide assistance and guidance to the design team for the procurement of long lead items, constructability, budget, and schedule.


Alternative Options:
The alternative would be not to make these adds to the scope of the Construction Manager At Risk and to defer needed upgrades and maintenance to the building's infrastructure.



Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
_ Flooding
_ Environment
X Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
05.25.21
277
FIM Approval
06.29.21
11
RFQ Advertisement - Architecture Services
01.04.22
207
Contract Awar...