Legislation Details

File #: 24-4137    Version: 1 Name:
Type: Utility Agreement Status: Passed
File created: 7/2/2024 In control: Commissioners Court
On agenda: 7/15/2024 Final action: 7/15/2024
Title: Request for approval to execute an agreement with CenterPoint Energy Houston Electric, LLC, in the amount of $49,423 to relocate power poles within Deussen Park, in connection with Deussen Park - Trails, Waterfront, and Parking - 2021, UPIN 22101MF2F801, Precinct 1.
Attachments: 1. 24-4137-Utility Agreement- - CPE Pole Relocation - Deussen Park - P1-07-15-24-24GEN1419_WO108926133
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Utility Agreement

Project ID (if applicable): 22101MF2F801
Vendor/Entity Legal Name (if applicable): CenterPoint Energy

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with CenterPoint Energy Houston Electric, LLC, in the amount of $49,423 to relocate power poles within Deussen Park, in connection with Deussen Park - Trails, Waterfront, and Parking - 2021, UPIN 22101MF2F801, Precinct 1.
end

Background and Discussion:
The project is to construct waterfront structures, parking lot, boardwalk, trail, lighting and landscape in both Alexander Deussen and Dwight D. Eisenhower Parks. It also includes the construction of a two span, signature pedestrian bridge with parapet panel over West Canal at Aqueduct Road to provide the pedestrian, hike and bike connection between Deussen Park and Eisenhower Park as part of the park trail system. The West Canal pedestrian bridge construction requires CenterPoint Energy to relocate the power poles within Deussen Park for both construction and permanent conditions. These conflict power poles are within the existing utility easement.

Expected Impact:
This action will resolve the conflict condition and provide safe zone during the construction.

Alternative Options:
No action will result in the conflicting condition and unsafe construction environment.

Alignment with Goal(s):
X Justice and Safety
_ Economic Opportunity
_ Housing
X Public Health
X Transportation
_ Flooding
_ Environment
X Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
N/A
N/A
N/A

Location: Alexander Deussen Park