Legislation Details

File #: 24-4099    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 7/2/2024 In control: Commissioners Court
On agenda: 7/15/2024 Final action: 7/15/2024
Title: Request for approval of a change in contract with Texas Materials Group, Inc., in connection with Transportation Improvements near University of Houston - Cullen Boulevard (Segment B) from South of Wheeler Ave to IH45 - 2019, adding 41 calendar days, with an addition in the amount of $10,452.00, Job No. 20/0124-3, UPIN 19101MF19201, Precinct 1, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 20/0124, UPIN 19101MF19201
Vendor/Entity Legal Name (if applicable): Texas Materials Group, Inc.

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Texas Materials Group, Inc., in connection with Transportation Improvements near University of Houston - Cullen Boulevard (Segment B) from South of Wheeler Ave to IH45 - 2019, adding 41 calendar days, with an addition in the amount of $10,452.00, Job No. 20/0124-3, UPIN 19101MF19201, Precinct 1, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
end

Background and Discussion:
Project includes reconstruction of Cullen Blvd to a 3-lane concrete boulevard with 12 feet wide share use path on each side including streetlights, trees, storm sewer, and 6 signals.

This Change in contracts includes:
- PCO-4 (Item #86) - Furnish and Install 12-inch pressure rated (150 pounds per square inch) polyvinyl chloride water line with restrained joints in steel casing, complete in place. Cost proposal for extending 20-inch steel casing for water line ($10,452.00 - 1 day).

- PCO-5 - Grades adjustment and revised on the proposed sidewalk elevations to properly drain area near the metro rail ($0.00 - 10 days).

- PCO-6 - Adding four tree grates to the new design with alignment on the sidewalk ($0.00 - 30 days).

Expected Impact:
Change allows the contractor to be compensated for additional item quantity and to extend the project term.

Alternative Options:
Continue with the project in...