Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 19/0305, UPIN 16101MF0H401
Vendor/Entity Legal Name (if applicable): Allgood Construction Co., Inc.
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Allgood Construction Co., Inc. in connection with final construction of Tidwell Road from West of Greens Bayou to CE King Parkway, adding 515 calendar days, with a deduction in the amount of $138,104.45, Job No. 19/0305-4, Precinct 1, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
end
Background and Discussion:
Project includes the construction of 4-Lane Concrete Boulevard and a new bridge at Greens Bayou. The roadway pavement had been constructed and used long before the new bridge completion. The work changes are the following:
* Relocation of Inlet at Station 12+25 LT in the additional amount of $3,500.00 and an additional 10 days.
* Construction to re-stripe the existing asphalt from the transition on the west of the project towards the west with $0.00 and additional 1 day.
* To refresh striping and buttons between John Ralston and CE King that was previously placed when traffic was opened to 4 lanes with $0.00 and additional 1 day.
* Requesting additional days due to the following: Tropical Storm Beta, RFI#018, RFI#009, RFI#003 and delay due to material and trucking shortage during bridge construction. with $0.00 and additional 198 days.
* Final Adjustments in the amount (deduction) of -$141,604.45 with zero days.
* Contractor (Allgood) is requesting additi...
Click here for full text