File #: 24-4056    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 6/28/2024 In control: Commissioners Court
On agenda: 7/15/2024 Final action: 7/15/2024
Title: Request for approval of a change in contract with Specialty Construction TX, LLC, in connection with Fallbrook, Ridgepoint, and Westpoint Subdivision Drainage Improvements - 2018, adding five calendar days, Job No. 23/0074-3, UPIN 19104MF13401, Precinct 2, MWDBE Contracted Goal: 27.00%, MWDBE Current Participation: 11.94%.
Sponsors: Mony Hossain
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): UPIN - 19104MF13401 - Job No. 23/0074
Vendor/Entity Legal Name (if applicable): Specialty Construction TX, LLC

MWDBE Contracted Goal (if applicable): 27.00%
MWDBE Current Participation (if applicable): 11.94%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Specialty Construction TX, LLC, in connection with Fallbrook, Ridgepoint, and Westpoint Subdivision Drainage Improvements - 2018, adding five calendar days, Job No. 23/0074-3, UPIN 19104MF13401, Precinct 2, MWDBE Contracted Goal: 27.00%, MWDBE Current Participation: 11.94%.
end

Background and Discussion:
The location of the work is in the Fallbrook, Ridgepoint, and Westpoint Subdivisions in the Halls Bayou Watershed. The proposed improvements include installation of new storm sewer system, roadway paving, channel restoration and desilting.

The Change in contract request includes the following:

* Addition of grade 1 riprap - Added 325.06 square yard of Grade 1 riprap to line item #47, at $110 per square yard for a total of $35,756.60. Deducted 1,430.264 square yard from line item #82, seal slab at $25.00 per square yard for a total deduction of $35,756.60 with an net change in the amount of $0.00 and added 5 days to the contract.
* Reconciliation of overrun line items - Added 22 square yards to Line item #5, Remove & Dispose Existing Concrete (Backslope Interceptor) at $40.00 per square yard for a total of $880.00. Added 6 linear feet to line item #33, 60-inch Reinforced Concrete Pipe, C-76, CL III, at $485.00 per linear foot for a total of $2,910.00. Added 10 square yards to line item #48, Reinforced Concrete Slope Paving (5") at $100.00 per squa...