Legislation Details

File #: 24-4036    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 6/27/2024 In control: Commissioners Court
On agenda: 7/15/2024 Final action: 7/15/2024
Title: Request for approval of a change in contract with E.P. Brady, Ltd., in connection with Kingslake Forest Subdivision Drainage Improvements - 2018, with an addition in the amount of $55,019.34, Job No. 22/0348-5, Bond Fund, UPIN 19101MF17A01, Precinct 1, MWDBE Contracted Goal: 20%, MWDBE Current Participation: 19.68%.
Sponsors: Mony Hossain
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 22/0348 - UPIN 19101MF17A01
Vendor/Entity Legal Name (if applicable): E.P. Brady, Ltd.

MWDBE Contracted Goal (if applicable): 20%
MWDBE Current Participation (if applicable): 19.68%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with E.P. Brady, Ltd., in connection with Kingslake Forest Subdivision Drainage Improvements - 2018, with an addition in the amount of $55,019.34, Job No. 22/0348-5, Bond Fund, UPIN 19101MF17A01, Precinct 1, MWDBE Contracted Goal: 20%, MWDBE Current Participation: 19.68%.
end

Background and Discussion:
Kingslake Forest Subdivision is located in Northeast Harris County, Texas, Precinct 1. Under existing conditions,
the Kingslake Forest Subdivision has experienced flood damage during extreme rainfall events. The project will
include storm sewer improvements along multiple streets in the neighborhood. The proposed drainage
improvements will consist of removal and replacement of existing storm sewers, as well as replacement of the
inlets. A detention basin will also be added to the southeastern portion of the neighborhood, to mitigate for
the impacts to Greens Bayou tributary P127-00-00 from the aforementioned improvements. This detention
basin will be dry bottom basin, with a perimeter concrete trail. The basin may include recreational features such as mature trees, signage, trash receptables, and benches.

The Change in contract request includes added quantities for the following:
* Waterline Conflict - Remove and Replace - Added 3 EACH to Item No. 87 - Waterline Conflict - Vertical Offset and added 2 EACH to Item No. 103 - Waterline Conflict - Remove and Replace with an ad...

Click here for full text