File #: 24-4034    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 6/27/2024 In control: Commissioners Court
On agenda: 7/15/2024 Final action: 7/15/2024
Title: Request for approval of a change in contract with CE Barker Ltd., in connection with Barrett Station (Phase 1 - Dreamland Place) Subdivision Drainage Improvements aka Barrett Station Drainage Improvements Project, adding 62 calendar days, Job No. 23/0278-3, Bond Fund, UPIN 19102MF17801, Precinct 3, MWDBE Contracted Goal: 26%, MWDBE Current Participation: 23.78%.
Sponsors: Mony Hossain
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): UPIN 19102MF17801; Job No: 23/0278
Vendor/Entity Legal Name (if applicable): CE Barker Ltd.

MWDBE Contracted Goal (if applicable): 26%
MWDBE Current Participation (if applicable): 23.78%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with CE Barker Ltd., in connection with Barrett Station (Phase 1 - Dreamland Place) Subdivision Drainage Improvements aka Barrett Station Drainage Improvements Project, adding 62 calendar days, Job No. 23/0278-3, Bond Fund, UPIN 19102MF17801, Precinct 3, MWDBE Contracted Goal: 26%, MWDBE Current Participation: 23.78%.
end

Background and Discussion:
Barrett Station (Phase 1 - Dreamland Place) Subdivision Drainage Improvements project is in the Northeast area of Harris County, east of FM 2100 and north of FM 1942. The scope of this project includes regrading roadside ditches, replace undersized driveway culverts, removal and replacement of driveways, road replacement in certain sections and construction of a dry bottom detention basin with pump station on the northeast corner of the subdivision, south of East Broussard.

The Change in contract request includes the following:

* Lift Station redesign: Adding additional days to contract due to an increase in water well dimensions, PLC removal in lieu of a pump controller, new electrical requirement and longer lead times for deliveries for an additional 62 days. - $0.00 - 62 days.

Expected Impact:
This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the Barrett Station (Phase 1 - Dreamland Place) subdivision.

Alternative Options...