Legislation Details

File #: 24-3830    Version: 1 Name:
Type: Interlocal Agreement Status: Passed
File created: 6/13/2024 In control: Commissioners Court
On agenda: 6/25/2024 Final action: 6/25/2024
Title: Request for approval to execute an Easement Conveyance Agreement with Coastal Water Authority (CWA) to construct an overpass across their Right of Way (ROW) as part of the State Highway (SH) 225/Sam Houston Tollway East Interchange Project (Precinct 2).
Attachments: 1. 24-3830 - Easement Conveyance
Department: Toll Road Authority
Department Head/Elected Official: Roberto Trevi?o, P.E., Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Interlocal Agreement

Project ID (if applicable): E18-0349
Vendor/Entity Legal Name (if applicable): Coastal Water Authority

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Request Summary (Agenda Caption):
title
Request for approval to execute an Easement Conveyance Agreement with Coastal Water Authority (CWA) to construct an overpass across their Right of Way (ROW) as part of the State Highway (SH) 225/Sam Houston Tollway East Interchange Project (Precinct 2).
end

Background and Discussion:
On February 23, 2023, the Texas Transportation Commission authorized the connection of the Sam Houston Tollway at State Highway 225 partial interchange and the development of an agreement between Harris County and TxDOT. This agreement was approved by the Commissioners Court on April 25, 2023, and is for the design, construction, and maintenance of five direct connectors and the design of the remaining three direct connectors at the interchange.

On April 23, 2024, Commissioners Court approved the advertisement of the first construction package which consists of four of the direct connectors (northbound/ westbound, northbound/eastbound, southbound/westbound, and southbound/eastbound), the widening of the westbound State Highway 225 mainlanes for entrance/exit ramp construction, and the reconstructing of the eastbound State Highway 225 frontage road to provide room for the direct connectors.

The Easement Agreement with CWA is needed for the construction of the southbound/westbound direct connector over CWA's Right Of Way.

Expected Impact:
Approval of the Easement Agreement will allow Harris County to complete the construction of the southbound/westbound direct connector.


...