Legislation Details

File #: 24-3748    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 6/13/2024 In control: Commissioners Court
On agenda: 6/25/2024 Final action: 6/25/2024
Title: Request for approval of a change in contract with CE Barker Ltd., in connection with Barrett Station (Phase 1 - Dreamland Place) Subdivision Drainage Improvements aka Barrett Station Drainage Improvements Project, adding 27 calendar days, Job No. 23/0278-1, Bond Fund, UPIN 19102MF17801, Precinct 3, MWDBE Contracted Goal: 26%, MWDBE Current Participation: 14.78%.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): UPIN 19102MF17801; Job No: 23/0278
Vendor/Entity Legal Name (if applicable): CE Barker Ltd.

MWDBE Contracted Goal (if applicable): 26%
MWDBE Current Participation (if applicable): 14.78%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with CE Barker Ltd., in connection with Barrett Station (Phase 1 - Dreamland Place) Subdivision Drainage Improvements aka Barrett Station Drainage Improvements Project, adding 27 calendar days, Job No. 23/0278-1, Bond Fund, UPIN 19102MF17801, Precinct 3, MWDBE Contracted Goal: 26%, MWDBE Current Participation: 14.78%.
end

Background and Discussion:
Barrett Station (Phase 1 - Dreamland Place) Subdivision Drainage Improvements project is in the Northeast area of Harris County, east of FM 2100 and north of FM 1942. The scope of this project includes regrading roadside ditches, replace undersized driveway culverts, removal and replacement of driveways, road replacement in certain sections and construction of a dry bottom detention basin with pump station on the northeast corner of the subdivision, south of East Broussard.

The Change in contract request includes the following:

* Utility Relocations: Adding additional days to contract relocation for sanitary sewer, waterlines and remove and abandon existing sanitary sewer and waterlines/project time due to conflict with proposed storm sewer based on the field conditions where the Municipal Utility District need to redesign the existing sewer service lead, manholes, sewer service lines and water lines that were not initially shown to be a conflict as per the design plans for an additional 15 days.
* Detention Pond Fish Relocati...