Legislation Details

File #: 24-3744    Version: 1 Name:
Type: Transmittal Status: Accepted
File created: 6/13/2024 In control: Commissioners Court
On agenda: 6/25/2024 Final action: 6/25/2024
Title: Transmittal by the Office of the County Engineer of a substantial completion certificate with Conrad Construction Co., LTD for improvements in connection with Water Control Improvement District (WCID) 50 Drainage Improvement - 2020, UPIN 21102MF1WF01, Precinct 2, MWDBE Contracted Goal: 9%, MWDBE Current Participation: 8.68%.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Transmittal

Project ID (if applicable): UPIN 21102MF1WF01 - Job No. 21/0195
Vendor/Entity Legal Name (if applicable): Conrad Construction Co., LTD

MWDBE Contracted Goal (if applicable): 9%
MWDBE Current Participation (if applicable): 8.68%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Transmittal by the Office of the County Engineer of a substantial completion certificate with Conrad Construction Co., LTD for improvements in connection with Water Control Improvement District (WCID) 50 Drainage Improvement - 2020, UPIN 21102MF1WF01, Precinct 2, MWDBE Contracted Goal: 9%, MWDBE Current Participation: 8.68%.
end

Background and Discussion:
The Substantial Completion Certificate provides documentation that a capital improvement project meets the qualifications of Substantial Completion in accordance with the Contract Documents as determined by the County Engineer. Substantial Completion establishes the date on which a capital improvement enters service as a Harris County asset. The establishment and reporting of this date is important for all governmental entities as outlined in the GASB Statement #34, Capital Assets & Depreciation Guidance, August 31, 2001. These certificates provide a method by which Harris County may document and record this date.

Expected Impact:

Alternative Options:

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
X Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
08/24/2021
21-4442
Contract Award
05/10/2022
22-2825
Change Order Approved
06/28/2022
22-3863
Change Order Approved
06/28/2022
22-3864
Change Order Approved
10/11/2022
22-6208
Cha...

Click here for full text