Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 23/0317; UPIN: 19103MF12J01
Vendor/Entity Legal Name (if applicable): CE Barker Ltd.
MWDBE Contracted Goal (if applicable): 23%
MWDBE Current Participation (if applicable): 8.88%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with CE Barker Ltd., in connection with Bernadine Estates & Tower Oaks Sec 3 Subdivision Drainage Improvements - 2018 aka Bernadine Drainage Improvements Project, adding 54 calendar days, Job No. 23/0317-2, UPIN 19103MF12J01, Precinct 3, MWDBE Contracted Goal: 23%, MWDBE Current Participation: 8.88%.
end
Background and Discussion:
The project is located in northwest Harris County in the White Oak Bayou watershed. Bernadine subdivision improvements consists of roadside ditches that drain into HCFCD channel E132-00-00. The scope and proposed improvements are to regrade roadside ditches, install a storm sewer system under the ditches, upsize culverts, and reconstruct roadways within the neighborhood. A detention pond will be constructed to mitigate within the project limits. Improvements will comply with Harris County standards. This agreement for Construction Phase Services provided by Ward, Getz & Associates, PLLC (WGA), ensures that the project is built in accordance with the Harris County and Harris County Flood Control regulations.
The Change in contract request new items for the following:
Revised Traffic Control Plan for Recovery Schedule - The additions of 54 contractual days due to traffic control plan revisions for the Asphalt Paving operations for Bernadine Estates. The revisions include long term closures, and the rephasing plan submitted by the Contractor for opti...
Click here for full text