File #: 24-3639    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 6/11/2024 In control: Commissioners Court
On agenda: 6/25/2024 Final action: 6/25/2024
Title: Request for approval of a change in contract with Precise Services, Inc., in connection with Parkway Forest Subdivision Drainage Improvements - 2018, adding 25 calendar days, with an addition in the amount of $54,478.00, Job No. 23/0238-1, UPIN 19101MF14P01, Precinct 1, MWDBE Contracted Goal: 31%.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): UPIN 19101MF14P01; Job No: 23/0238
Vendor/Entity Legal Name (if applicable): Precise Services, Inc.

MWDBE Contracted Goal (if applicable): 31%
MWDBE Current Participation (if applicable): 0%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Precise Services, Inc., in connection with Parkway Forest Subdivision Drainage Improvements - 2018, adding 25 calendar days, with an addition in the amount of $54,478.00, Job No. 23/0238-1, UPIN 19101MF14P01, Precinct 1, MWDBE Contracted Goal: 31%.
end

Background and Discussion:
Parkway Forest is in Northeast Harris County, Texas, Precinct 1. The subdivision is mainly composed of single-family homes. The residents have experienced structural flooding during several recent flood events. The purpose of this project is to reduce flooding for homes. The proposed solution includes upgrading storm sewers and adding a detention pond.

The Change in contract request includes the following:

* Clearing and grubbing: An additional quantity of 0.87 AC of Clearing and grubbing is needed for the existing line item #050 to complete the work as proposed in the design plan with an additional cost of $12,180.00 and 0 days.
* Revised scope for storm sewer installation: Change in construction scope of work adding new line items and additional contract/project time due to existing storm line conflicting Traffic Control Plans along Parkway Forest Drive. The new line items are Flowable Fill, Reinforced Concrete Pipe 42-inch Plug, and Reinforced Concrete Pipe 36-inch plug. There will also be a deduction on the line item for the removal and disposal of the existing storm sewer pipe. There w...