Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 23/0087, UPIN 21035MF1QK01
Vendor/Entity Legal Name (if applicable): Icon GC, LLC
MWDBE Contracted Goal (if applicable): 18%
MWDBE Current Participation (if applicable): 0%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Icon GC, LLC, in connection with HCSFNC - TO4 - Vista 'Baker Ripley Site', with an addition in the amount of $38,933.27, Job No. 23/0087-5, UPIN 21035MF1QK01, Precinct 2, MWDBE Contracted Goal: 18%.
end
Background and Discussion:
The project includes the construction of water distribution system, wastewater collection system, storm water system and road paving for Orchard Place Subdivision for Harris County Precinct 2.
The change order includes the following:
- It was determined by City of Pasadena that the initial pavement did not meet their preference and aesthetics, and to emphasizes the commitment to meeting the standards set by the City of Pasadena and ensuring the quality and longevity of the road infrastructure. It was decided to remove and reinstall the concrete pavement. This change will add $19,817.63 and no additional days to the contract.
- The purpose of Preserve E has shifted to serve as a recreational area, prompting the removal of excess dirt and the leveling of the terrain according to revised elevation plans approved by the engineer. This change will add $19,115.64 and no additional days to the contract.
Expected Impact:
Increase the total cost for the contract.
Alternative Options:
No action will result in substandard construction.