Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E, PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 23/0152, UPIN 19101MF0XY01
Vendor/Entity Legal Name (if applicable): Conrad Construction Co., Ltd.
MWDBE Contracted Goal (if applicable): 21%
MWDBE Current Participation (if applicable): 0%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Conrad Construction Co., Ltd. in connection with Anderson Road - Hiram Clarke Road to Almeda Road - 2018, adding 24 calendar days, with an addition in the amount of $70,650.00, Job No. 23/0152-1, UPIN 19101MF0XY01, Precinct 1, MWDBE Contracted Goal: 21%.
end
Background and Discussion:
Project includes completion of the two-lane concrete curb and gutter road with sidewalk on both sides and left turn lanes at the intersections approximately 7,800 linear feet of Anderson Road construction from 500 feet west of Hiram Clark Road to Almeda Road/FM 521 (Segment 2).
This change in contracts includes:
Item #97 - Low-Profile Concrete Barrier (Relocate) - Increase Low-Profile Concrete Barrier quantity 400 linear feet. Concrete barrier is needed during storm sewer construction and allow for Center Point Energy relocation of gas line ($12,800.00 - 14 days).
Item # 159 - Furnish and Install barbed wire fence at detention pond (Includes demolition of existing fence) - Cost proposal for the removal or replacement of 2,750 linear feet of barbed wire fence around the newly acquired right of way for the pond work ($32,050.00 - 3 days).
Item #152 - Well Pointing (Minimum Bid $25/linear feet) - Well pointing needed to remove the groundwater for storm sewer installation - Increase well pointing quantity 500 linear feet ($15,000.00 - 7 days).
Item #157 - Temporary Pavement Mark...