Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 22/0344, UPIN 18103N302202
Vendor/Entity Legal Name (if applicable): Sequeira Civil Construction, LLC
MWDBE Contracted Goal (if applicable): 100%
MWDBE Current Participation (if applicable): 100%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Sequeira Civil Construction, LLC, in connection with final construction of Schiel Road 1 - from East of SH-99 to West of Fairfield Place Drive, adding five calendar days, with a deduction in the amount of $93,443.22, Job No. 22/0344-3, UPIN 18103N302202, Precinct 3, MWDBE Contracted Goal: 100%, MWDBE Current Participation: 100%.
end
Background and Discussion:
The project includes construction of a standard 4-lane concrete boulevard section on Schiel Road, from East of State Highway 99 to West of Fairfield Place Drive.
This change in contracts includes:
* Cost of furnish and installation of pipe gates in front of Harris County Flood Control District access road. ($22,295.54)
* Cost and time for tie in offsite drainage pipe to the back of an inlet in front of soccer field at west end of the project. ($7,162.85 - 2 days)
* Cost and time for installation of urban interceptor at the end of 24-inch pipe between TXDOT right of way and detention pond. ($12,499.64 - 3 days).
* The final adjustment (reconciliation of actual quantities used in construction against the bid quantities). Total = -$135,401.22
Expected Impact:
Change allows unused funds to be returned to Harris County and allows the Contractor to be compensated for actual work.
Alternative Options:
Maintain the original scope of the project.
Alignment with Goal(s):
_ Justice and Safety
...
Click here for full text