Legislation Details

File #: 24-3332    Version: 1 Name:
Type: Grant Status: Passed
File created: 5/23/2024 In control: Commissioners Court
On agenda: 6/4/2024 Final action: 6/4/2024
Title: Request by the Flood Control District for approval to accept from the Texas Water Development Board grant funds in the amount of $12,000,000, with no required match, for the T.C. Jester Stormwater Detention Basin Program (Cypress Creek Watershed, Project ID K500-23-00-E004, Precinct 3).
Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Grant

Project ID (if applicable): K500-23-00-E004
Vendor/Entity Legal Name (if applicable): Texas Water Development Board

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Request Summary (Agenda Caption):
title
Request by the Flood Control District for approval to accept from the Texas Water Development Board grant funds in the amount of $12,000,000, with no required match, for the T.C. Jester Stormwater Detention Basin Program (Cypress Creek Watershed, Project ID K500-23-00-E004, Precinct 3).
end

Background and Discussion:
It is recommended that the Flood Control District be authorized to accept the grant award funds from the Texas Water Development Board from Texas legislative action (state Community Directed Funding) to fund the the TC Jester Stormwater Detention Basin Project. TWDB funding efforts were led by Rep. Sam Harless. This project has also received Congressionally directed grant funding assistance from the Federal Emergency Management Agency (FEMA) Legislative Pre-Disaster Mitigation (LPDM) program providing up to $9,886,000 for design and construction, as well as Community Development Block Grant (CDBG) funding, providing up to $21,000,000 for design and construction. FEMA funding efforts were led by Rep. Dan Crenshaw.

The project consists of the construction of three wet-bottom stormwater detention basins (Basin 1a, 1b and 2). The proposed TWDB legislation allocation grant is for a portion Basin 1b only. The remaining volume in Basin 1b will be constructed with CBDG-MIT grant funds. The basins (1a and 2) will be constructed with Federal Emergency Management Agency grant funds.

The proposed stormwater detention basins (Bain 1a, 1b and 2) ...

Click here for full text