Legislation Details

File #: 24-3300    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 5/23/2024 In control: Commissioners Court
On agenda: 6/4/2024 Final action: 6/4/2024
Title: Request for approval of an amendment to a utility adjustment agreement with CenterPoint Energy Resources Corp. dba CenterPoint Energy Texas Gas Operations, in the amount of $145,678.41, to provide additional scope required for the utility relocation on HCFCD Unit K142-00-00. (Cypress Creek Watershed, Project ID Z100-00-00-X282, Agreement No. 2020-102, Precinct 3).
Attachments: 1. 060424 AMEND CENTERPOINT 2020-102 PCT 3 backup.pdf
Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Z100-00-00-X282
Vendor/Entity Legal Name (if applicable): CenterPoint Energy Resources Corp. dba CenterPoint Energy Texas

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Request Summary (Agenda Caption):
title
Request for approval of an amendment to a utility adjustment agreement with CenterPoint Energy Resources Corp. dba CenterPoint Energy Texas Gas Operations, in the amount of $145,678.41, to provide additional scope required for the utility relocation on HCFCD Unit K142-00-00. (Cypress Creek Watershed, Project ID Z100-00-00-X282, Agreement No. 2020-102, Precinct 3).
end

Background and Discussion:
The original agreement made with CenterPoint Energy Texas Gas Operations was in the amount of $56,070.49; however, additional scope was required to minimize impacts to adjacent residents. The additional scope required to complete the utility relocation work totaled $145,678.41. The total amended agreement amount is $201,748.90.

Expected Impact:
If this agreement is approved, it will allow for the completion of payment for the utility relocation work. Relocating the CenterPoint Energy gas line allowed Flood Control District to complete the planned rehabilitation project as designed. Restoring the channel back to the original design capacity protects the public and public infrastructure by allowing for the proper conveyance of water. The repairs also reduce the risk of flooding in the future.

Alternative Options:
There are no alternate options as CenterPoint is the one and only entity we can deal with in these matters.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Hea...