Legislation Details

File #: 24-3295    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 5/23/2024 In control: Commissioners Court
On agenda: 6/4/2024 Final action: 6/4/2024
Title: Request for approval of a change in contract with Specialty Construction TX, LLC, in connection with Fallbrook, Ridgepoint, and Westpoint Subdivisions Drainage Improvements - 2018, adding three calendar days, with an addition in the amount of $38,842.00, UPIN 19104MF13401, Precinct 2, MWDBE Contracted Goal: 27.00%, MWDBE Current Participation: 13.78%.
Sponsors: Mony Hossain
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): UPIN - 19104MF13401 - Job No. 23/0074
Vendor/Entity Legal Name (if applicable): Specialty Construction TX, LLC

MWDBE Contracted Goal (if applicable): 27.00%
MWDBE Current Participation (if applicable): 13.78%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Specialty Construction TX, LLC, in connection with Fallbrook, Ridgepoint, and Westpoint Subdivisions Drainage Improvements - 2018, adding three calendar days, with an addition in the amount of $38,842.00, UPIN 19104MF13401, Precinct 2, MWDBE Contracted Goal: 27.00%, MWDBE Current Participation: 13.78%.
end

Background and Discussion:
The location of the work is in the Fallbrook, Ridgepoint, and Westpoint Subdivisions in the Halls Bayou Watershed. The proposed improvements include installation of new storm sewer system, roadway paving, channel restoration and desilting.

The Change in contract request includes the following:

* PCO #7 - Drainage ditch P118-31-02 draining in to P118-31-00 - An addition of quantities to existing line items #31- 24-inch Reinforced concrete pipe by 48 liner feet, #47-Grade 1 Riprap by 122.2 square yards since the items overran the original commitment amount. Adding a new line for Remobilization and demobilization and temporary dirt dam and dewatering as per revised design plans. Additional quantities for above line items#31 and #47 and added 1 lumpsum for items #91-Remobilization and demobilization and 1 lumpsum for #92- Temporary dirt dam and dewatering are needed to complete the work as proposed in the revised design plans, for an additional cost of $24,742.00 and 3 days.
* PCO #8 - Construction safety fence - Add...

Click here for full text