Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Frost Construction Company, Inc. in connection with Maintenance Barn at Deussen Park - Renovation - 2022, adding 16 calendar days, with an addition in the amount of $79,598.36, Job No. 23/0435, UPIN 22101MF26401, Precinct 1, MWDBE Contracted Goal: 20%, MWDBE Current Participation: 20%.
end
Background and Discussion:
This project was designed to improve the maintenance barn at Deussen Park. Structural work was needed due to the age of the building as well as exposure to the elements. The structure is also receiving a new and improved interior, exterior shell, and improved drainage to help mitigate future exposure.
Expected Impact:
This CIC is needed due to discovered existing conditions of the structure that was not apparent until after the demolition was completed, also included is a slight design change for the doors to better match the new shell that will be installed as requested by the precinct, the proposed trench drain also needs to be extended to get rid of existing ponding, and additional electrical work is required to correct existing issues that will bring the building to code.
The structural additions will help improve the stability of the structure and are being cited as required by the structural engineer. The addition of the door will better match the proposed new shell. The trench drain extension will pull water away from the building and increase the longevity of the...