Legislation Details

File #: 24-3216    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 5/22/2024 In control: Commissioners Court
On agenda: 6/4/2024 Final action: 6/4/2024
Title: Request for approval to rescind an award from Sterling Site Services, LLC. in connection with an award approved by Commissioners Court on January 30, 2024 and approve a new award on the basis of low bid to Solid Bridge Construction in the amount of $7,256,197 for expansion and enhancement of the Cypress Detention Basin - 2021 for Precinct 3, and for the County Clerk to execute any applicable bonds to be received, with certain items not being awarded (230463), MWDBE Contracted Goal: 24%.
Department: Purchasing
Department Head/Elected Official: DeWight Dopslauf

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): 230463
Vendor/Entity Legal Name (if applicable): Solid Bridge Construction

MWDBE Contracted Goal (if applicable): 24%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval to rescind an award from Sterling Site Services, LLC. in connection with an award approved by Commissioners Court on January 30, 2024 and approve a new award on the basis of low bid to Solid Bridge Construction in the amount of $7,256,197 for expansion and enhancement of the Cypress Detention Basin - 2021 for Precinct 3, and for the County Clerk to execute any applicable bonds to be received, with certain items not being awarded (230463), MWDBE Contracted Goal: 24%.
...end

Background and Discussion:
Project involves expansion of the existing wet bottom stormwater detention basin by excavating and disposing of about 160,000 cubic yards of soil thereby expanding the basin by about 48.60 acre-feet. The Project also intends to add detention capacity by constructing a system to preemptively release water and lowering the water surface elevation in advance of major storms. It includes a 48" outfall pipe from the pond which will release water through a remotely operated plug valve powered by a solar charged battery.

Expected Impact:
This action will allow Solid Bridge Construction to proceed with the construction of the project, therefore, reducing the flood risk of the community in the watershed.

Alternative Options:
If no action is taken, the construction of the project will not be completed, and the Cypress Park detention pond will continue for function under existent conditions.