File #: 24-3146    Version: 1 Name:
Type: Financial Authorization Status: Passed
File created: 5/20/2024 In control: Commissioners Court
On agenda: 6/4/2024 Final action: 6/4/2024
Title: Request for approval to pay the U.S. Army Corps of Engineers $21,460.00 for evaluation of REIN-23-009, application to construct channels within Addicks Reservoir in connection with Bear Creek Village Subdivision Drainage Improvements - 2018, UPIN 19104MF12M01.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA

Type of Request: Financial Authorization

Project ID (if applicable): UPIN 19101MF17901
Vendor/Entity Legal Name (if applicable): Department of the Army, U.S. Army Corps of Engineers, Galveston District

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable):
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Request Summary (Agenda Caption):
title
Request for approval to pay the U.S. Army Corps of Engineers $21,460.00 for evaluation of REIN-23-009, application to construct channels within Addicks Reservoir in connection with Bear Creek Village Subdivision Drainage Improvements - 2018, UPIN 19104MF12M01.
end

Background and Discussion:
The Bear Creek Village Subdivision is 675 acres generally bound by Clay Road to the south, State Highway
6 to the west, Addicks Satsuma Road to the north, and the Addicks Reservoir to the east. The structures in the subdivision have suffered repetitive flood losses. Most recently, during Hurricane Harvey, 1,396 structures were flooded. Prior to that, the Tax Day flood in April 2016 flooded 306 structures. Drainage problems within the Bear Creek Village Subdivision primarily result from ponding areas where the storm sewer system is inadequate to collect and drain extreme event runoff. Drainage analysis has shown that street regrading and storm sewer replacement, in addition to channels in the reservoir, will provide the optimal reduction in flooding for the subdivision. The USACE will need to provide a construction license to allow the channels to be constructed within the reservoir. USACE has requested payment of fee prior to completion of the evaluation of the submitted application.

Expected Impact:
This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in th...