Title: Request for discussion and possible action for approval of the H T & J, LLC. professional services contract for the Stone Ridge Subdivision Drainage Improvements - 2018, UPIN 19103MF12X01, Precinct 3, in connection with an item previously approved by Commissioners Court on February 21, 2023.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Discussion Item

Project ID (if applicable): UPIN-19103MF12X01
Vendor/Entity Legal Name (if applicable): H T & J, LLC.

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Request Summary (Agenda Caption):
title
Request for discussion and possible action for approval of the H T & J, LLC. professional services contract for the Stone Ridge Subdivision Drainage Improvements - 2018, UPIN 19103MF12X01, Precinct 3, in connection with an item previously approved by Commissioners Court on February 21, 2023.
end

Background and Discussion:
The professional services contract was originally executed on June 04, 2019 with H T & J LLC. Per court action on February 21, 2023, this project was placed on Table 1- Projects on Hold Based on Feasibility and Non-cooperating Partners.

Expected Impact:
Approving this Discussion Item complies with the court action taken on February 21, 2023, for Table 1- Projects on Hold Based on Feasibility and Non-cooperating Partners.

Alternative Options:
No alternative option.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
X Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
04/30/2019
11
Authorization to Negotiate for Engineering Services
06/04/2019
16
Contract Award for Professional Engineering Services
10/08/2019|1010|Approval of Study Report
02/21/2023
37
Adoption of recommendations 1, 2, and 4 as presented and to add the following: Pause the project identified in Table 3 of item 37, pending additional partner participation or precinct funding