Legislation Details

File #: 24-3117    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 5/20/2024 In control: Commissioners Court
On agenda: 6/4/2024 Final action: 6/4/2024
Title: Request for approval of a change in contract with C.E. Barker Ltd., in connection with Western Homes Addition Subdivision Drainage Improvements - 2018, adding four calendar days, Job No. 22/0425-1, UPIN 20102MF1E501, Precinct 2, MWDBE Contracted Goal: 30.60%, MWDBE Current Participation: 34.27%.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): UPIN - 20102MF1E501 - Job No. 22/0425
Vendor/Entity Legal Name (if applicable): C.E. Barker Ltd.

MWDBE Contracted Goal (if applicable): 30.60%
MWDBE Current Participation (if applicable): 34.27%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with C.E. Barker Ltd., in connection with Western Homes Addition Subdivision Drainage Improvements - 2018, adding four calendar days, Job No. 22/0425-1, UPIN 20102MF1E501, Precinct 2, MWDBE Contracted Goal: 30.60%, MWDBE Current Participation: 34.27%.
end

Background and Discussion:
The location of the work is in the Western Homes Subdivision is in the Halls Bayou Watershed. The proposed improvements include installation of new storm sewer system, roadway paving, driveway paving, widening and regrading of existing roadside ditches, and detention pond improvements.

The change in contract includes the following:

* PCO #9 - Swapping proposed 12" RCP with trench drain -Field conditions led to installing trench drain instead of 12" RCPs called out on plans. There is enough underrunning on 12" RCP (line item #40), therefore no funding increase is necessary to extend the existing line item #38 by 36 LF. Extended the existing line item #38 by 36 LF, deducted from existing line item #40 by 91.75 LF. Added $0.00 and 2 days.
* PCO #10 -Added driveway on Stirrup Street - A driveway was added due to existing field conditions on Stirrup Street thereby potentially overrunning trench drain and concrete driveway line items #38 and #29 respectively. There is enough underrunning on line item #7 - pipe removal and disposal, which will remain unutilized for the remaining project and so...