Legislation Details

File #: 24-3116    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 5/20/2024 In control: Commissioners Court
On agenda: 6/4/2024 Final action: 6/4/2024
Title: Request for approval of a change in contract with Blazey Construction Services, LLC, in connection with Tower Oaks Plaza Subdivision drainage improvements - 2018, adding 180 calendar days, with an addition in the amount of $42,264.21, Job No. 23/0027, UPIN 19103MF14801, Precinct 3, MWDBE Contracted Goal: 31%, MWDBE Current Participation: 100%.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): UPIN: 19103MF14801- Job No.23/0027
Vendor/Entity Legal Name (if applicable): Blazey Construction Services, LLC

MWDBE Contracted Goal (if applicable): 31%
MWDBE Current Participation (if applicable): 100%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Blazey Construction Services, LLC, in connection with Tower Oaks Plaza Subdivision drainage improvements - 2018, adding 180 calendar days, with an addition in the amount of $42,264.21, Job No. 23/0027, UPIN 19103MF14801, Precinct 3, MWDBE Contracted Goal: 31%, MWDBE Current Participation: 100%.
end

Background and Discussion:
The project is in northwest Harris County, north of Cypress North Houston Road and east of North Eldridge Parkway. The existing drainage system consists of roadside ditches which outfall to the west of the subdivision via 24 to 36-inch pipes at three points along HCFCD Channel K161-00-00 and to Cypress Creek from a fourth outfall at the northeast corner of the subdivision. The scope and proposed improvements include bringing the subdivision roadways into compliance with Harris County Standards, constructing storm sewer underlying roadside ditches, regrading roadside ditches, upsizing, and replacing driveway culverts, replacing driveways, and the construction of a storm water detention basin.

The Change in contract request includes the following:

* PCO-3: An Addition of quantities to existing Line Items # 10-REMOVE AND DISPOSE OF EXISTING CONCRETE OR MEATL PIPE (ALL SIZES), #50-ADJUSTING MANHOLES AND INLETS, Item #58-CORREGATED METAL PIPE (36 inches) (PRECOATED)(GALVANIZED)(16 GUAGE) overran the original quantities due to field con...

Click here for full text