Title: Request for approval of a change in contract with CE Barker Ltd., in connection with Barrett Station (Phase 1 - Dreamland Place) Subdivision Drainage Improvements, adding 45 calendar days, Job No. 23/0278-1, UPIN 19102MF17801, Precinct 3, MWDBE Contracted Goal: 26%, MWDBE Participation Goal: 20.81%.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): UPIN 19102MF17801; Job No: 23/0278
Vendor/Entity Legal Name (if applicable): CE Barker Ltd

MWDBE Contracted Goal (if applicable): 26%
MWDBE Current Participation (if applicable): 20.81%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with CE Barker Ltd., in connection with Barrett Station (Phase 1 - Dreamland Place) Subdivision Drainage Improvements, adding 45 calendar days, Job No. 23/0278-1, UPIN 19102MF17801, Precinct 3, MWDBE Contracted Goal: 26%, MWDBE Participation Goal: 20.81%.
end

Background and Discussion:
Barrett Station (Phase 1 - Dreamland Place) Subdivision Drainage Improvements project is in the Northeast area of Harris County, east of FM 2100 and north of FM 1942. The scope of this project includes regrading roadside ditches, replace undersized driveway culverts, removal and replacement of driveways, road replacement in certain sections and construction of a dry bottom detention basin with pump station on the northeast corner of the subdivision, south of East Broussard.

The Change in contract request includes the following:

* PCO 1: Adding 15 days to contract time due to an increase in the addition of 16 driveways to be constructed due to field conditions that were not initially shown on the design plans.
* PCO 2: Adding 30 days to contract time due to field conditions where the Municipal Utility District need to redesign the existing sewer service lead, manholes, sewer service lines and water lines that were not initially shown to be a conflict as per the design plans.

Expected Impact:
This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the...