Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): UPIN 19101MF17A01 - Job No. 22/0348
Vendor/Entity Legal Name (if applicable): E.P. Brady, LTD
MWDBE Contracted Goal (if applicable): 20%
MWDBE Current Participation (if applicable): 15.73%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with E.P. Brady, LTD, in connection with Kingslake Forest Subdivision Drainage Improvements - 2018, adding 18 calendar days, Job No. 22/0348-4, UPIN 19101MF17A01, Precinct 1, MWDBE Contracted Goal: 20%, MWDBE Current Participation: 15.73%.
end
Background and Discussion:
Kingslake Forest Subdivision located in Northeast Harris County, Texas, Precinct 1. Under existing conditions, the Kingslake Forest Subdivision has experienced flood damage during extreme rainfall events. The project will include storm sewer improvements along multiple streets in the neighborhood. The proposed drainage improvements will consist of removal and replacement of existing storm sewers, as well as replacement of the
inlets. A detention basin will also be added to the southeastern portion of the neighborhood, to mitigate the impacts to Greens Bayou tributary P127-00-00 from the improvements. This detention basin will be a dry bottom basin, with a perimeter concrete trail. The basin may include recreational features such as mature trees, signage, trash receptables, and benches.
The Change in contract request includes the following:
* PCO - 7 Reinforced Box Culvert Materials - Added 8 days for an extension of contract time due to supplier accounting related issues affecting the delivery of storm sewer box culvert materials. The installation of the storm sewer box culverts is a critical path activity....
Click here for full text