Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 23/0260, UPIN 23103MF2P101
Vendor/Entity Legal Name (if applicable): Forde Construction Co.
MWDBE Contracted Goal (if applicable): 34%
MWDBE Current Participation (if applicable): 24%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Forde Construction Co., in connection with Bridge Repair - Brinsap 2020 Package 3 - 2022, adding 20 calendar days, with an addition in the amount of $233,509.80, Job No. 23/0260-1, UPIN 23103MF2P101, Precinct 3, MWDBE Contracted Goal: 34%, MWDBE Current Participation: 24%.
end
Background and Discussion:
The project includes various bridge repairs at six locations withing Harris County Precinct 3 (Jones Road at Cypress Creek, Louetta Road at Theiss Gully, Oak Lane at G103-01-00, Hardy Road South Bound at Cypress Creek Relief, Cypresswood Drive at Cypress Creek, and Tuckerton Road West Bound at Towne Lake Detention).
This change in contracts includes:
* Time and cost of additional repair and scope of work on Louetta Road at Theiss Gully based on field condition (installation of extra flowable fill underneath the abutment cap, concrete spall repair, pedestrian rail repair, erosion repair with cement stabilized sand on embankment underneath bridge and bridge longitudinal joint repair). $233,509.80 - 20 days
Expected Impact:
Change prevent and avoid further damage to the bridge and allows the Contractor to be compensated for proposed changes.
Alternative Options:
Maintain the original scope of the project and fix the repair later which may cause further damage to the bridge.
Alignment with Goal(s):
_ Justice and Safety