File #: 24-3097    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 5/20/2024 In control: Commissioners Court
On agenda: 6/4/2024 Final action: 6/4/2024
Title: Request for approval of a change in contract with Ballast Point Construction, Inc., in connection with Trail - Fairmont Parkway from HCFCD B100 to Red Bluff Drive - 2021, adding 12 calendar days, with an addition in the amount of $12,480.00, Job No. 23/0224-1, UPIN 22102MF2FC01, Precinct 2, MWDBE Contracted Goal: 30%, MWDBE Current Participation: 18.87%.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 23/0224, UPIN 22102MF2FC01
Vendor/Entity Legal Name (if applicable): Ballast Point Construction, Inc.

MWDBE Contracted Goal (if applicable): 30%
MWDBE Current Participation (if applicable): 18.87%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Ballast Point Construction, Inc., in connection with Trail - Fairmont Parkway from HCFCD B100 to Red Bluff Drive - 2021, adding 12 calendar days, with an addition in the amount of $12,480.00, Job No. 23/0224-1, UPIN 22102MF2FC01, Precinct 2, MWDBE Contracted Goal: 30%, MWDBE Current Participation: 18.87%.
end

Background and Discussion:
Construction of 10' wide trail along Fairmont Parkway from Armand Bayou Hike and Bike Trailhead to Red Bluff Drive, with a pedestrian bridge at Armand Bayou (B100-00-00). Proposed trail includes upgraded audio pedestrian signals, crosswalks, and ramps at signalized intersections at Center Street and Red Bluff Drive.

The change order includes the following:

- The need for tree removal in conflict with the pedestrian bridge was identified following discussions during the biweekly meeting. It was agreed upon that the removal of 4 trees, 2 trees on the southwest side of the channel's slope paving and two trees east of the channel. This change will add $12,480.00 and additional 3 days to the contract.

- The delays in project progress during the period from January 15th, 2024, to January 28th, 2024, were primarily attributed to adverse weather conditions, specifically freezing temperatures, and heavy rainfall, which hindered travel to the site, material delivery, and halted work due to wet site conditions. The extension req...