Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): 22/0019, UPIN 22103MF2E401
Vendor/Entity Legal Name (if applicable): GLM Contracting, Inc.
MWDBE Contracted Goal (if applicable): 19%
MWDBE Current Participation (if applicable): 28.02%
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with GLM Contracting, Inc., in connection with final construction of On-Call - Construction - General Civil, Precinct 3 - 2021, adding 84 calendar days, with an addition in the amount of $96,080.00, Job No. 22/0019-1, UPIN, 22103MF2E401, Precinct 3, MWDBE Contracted Goal: 19%, MWDBE Current Participation: 28.02%.
end
Background and Discussion:
Project includes General Civil services tasks for variety of locations throughout Precinct 3.
Expected Impact:
Change allows unused funds to be returned to the Precinct and allow the Contractor to be compensated for the actual work completed on the project.
Alternative Options:
Maintain the original scope of the project.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date
Agenda Item #
Action Taken
06/28/2022
304
Contract Award
Location:
Address (if applicable):
Precinct(s): Precinct 3
Fiscal and Personnel Summary
Service Name
Engineering
Current Fiscal Year Cost
Annual Fiscal Cost
Labor
Non-Labor
Total
Recurring Expenses
Funding Sources
Existing Budget
1070 - Mobility Fund
$
$96,080.00
$96,080.00
$
Choose an item.
$
$
$
$
Choose an item.
$
$
$
$
Total Current Budget
$
$96,080.00
$96,080.00
$
Additional Budget Request (Requires Fiscal Review Request Form)
Choose an item....
Click here for full text