Legislation Details

File #: 24-3051    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 5/16/2024 In control: Commissioners Court
On agenda: 6/4/2024 Final action: 6/4/2024
Title: Request for approval of a change in contract with John Reed and Company, LLC in connection with Brays Bayou Pedestrian/Bike Bridge near Stella Link/Glen Arbor, with an addition in the amount of $13,961.00, Job No. 23/0286-1, UPIN 19101MF0XZ01, Precinct 1, MWDBE Contracted Goal: 0% - Non-Divisible.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No: 23/0286, UPIN 19101MF0XZ01
Vendor/Entity Legal Name (if applicable): John Reed and Company, LLC

MWDBE Contracted Goal (if applicable): 0%
MWDBE Current Participation (if applicable): 0%
Justification for 0% MWDBE Participation Goal: 0% - Non-Divisible

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with John Reed and Company, LLC in connection with Brays Bayou Pedestrian/Bike Bridge near Stella Link/Glen Arbor, with an addition in the amount of $13,961.00, Job No. 23/0286-1, UPIN 19101MF0XZ01, Precinct 1, MWDBE Contracted Goal: 0% - Non-Divisible.
end

Background and Discussion:
The project is to construct a pedestrian bridge over Brays Bayou to connect the pedestrian facilities from North Braeswood Boulevard to South Braeswood Boulevard, east of Stella Link Road. The bridge has 3-spans with 226 feet length and approximate 400 feet ramps.
The change order includes the following:
* Additional 72.3 SY of 5" thick of black base for temporary sidewalk at $70.00 per SY = $5,061.00.
* Additional 3 EA trees removed at $2,000.00 per tree = $6,000.00.
* Additional 2 project signs installed at Northside, 1-regular project sign at $1,300.00 and 1-special project sign = $1,600.00. Total = $2,900.00.
* Total Additional Amount = $13,961.00 with zero days.

Expected Impact:
Provide safe pedestrian and cyclist crossing over Brays Bayou between North Braeswood Boulevard to South Braeswood Boulevard.

Alternative Options:
N/A

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
x Transportation
_ Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
09/19/2023
325
Contract Award

Location:
Ad...

Click here for full text