Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 23/0239, UPIN 18103N302203
Vendor/Entity Legal Name (if applicable): Sequeira Civil Construction, LLC
MWDBE Contracted Goal (if applicable): 32%
MWDBE Current Participation (if applicable): 100%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Sequeira Civil Construction, LLC, in connection with Schiel Road 2 - from West of Fairfield Place Drive to West of Mason Road, adding 31 calendar days, with an addition in the amount of $223,341.88, Job No. 23/0239-1, UPIN 18103N302203, Precinct 3, MWDBE Contracted Goal: 32%, MWDBE Current Participation: 100%.
end
Background and Discussion:
Project included the reconstruction of Schiel Road 2 - from West of Fairfield Place Drive to West of Mason Road. Reconstruction includes an upgrade of the roadway from a two-lane asphalt road with open ditches to a 4-lane concrete curb and gutter boulevard with a 32' raised median.
Change includes additional cost for the installation of school flashers, sidewalks, ramps, and reinforced concrete pipe quantities. Due to an error in stationing on the plans, the quantities were underestimated compared to the actual quantities required for a complete storm sewer system as called out on plans and school flashers were added as new item to the contract. This change in contract also included adding additional time delays due to unforeseen field conditions. This change order is necessary to properly compensate contractor for the additional work and time required.
New Item
SCHOOL ZONE FLASHERS $172,003.08
ADA RAMP - TYPE 9 $3593.20
Existing Item
REINFORCED CONCRETE PIPE (30") RUBBER GASKET $47,745.60
Expected Im...
Click here for full text