Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 22/0001, UPIN 20101MF1JH01
Vendor/Entity Legal Name (if applicable): DVL Enterprises, LLC
MWDBE Contracted Goal (if applicable): 18%
MWDBE Current Participation (if applicable): 24.81%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with DVL Enterprises, LLC, in connection with final construction of Sidewalk & Bikeway - El Camino & El Rio Street - 2020, adding 429 calendar days, with an addition in the amount of $169,326.08, Job No. 22/0001-2, UPIN 20101MF1JH01, Precinct 1, MWDBE Contracted Goal: 18%, MWDBE Current Participation: 24.81%.
end
Background and Discussion:
Project includes the installation of bike lanes and the construction of a 6-foot-wide concrete sidewalk on each
side of El Camino Street and El Rio Street from Holly Hall Street to El Rio Street.
Change includes:
* Additional Pre-Cast Concrete Bikeway Curb (6" x 14") at 3 locations, amount is $1,080.00 and 0 Days.
* Removal of existing stripe ceramic buttons located at new tire path, amount is $3,926.00 and 3 Days.
* Additional days needed due to lead time ordering on the Green Type C, Additional 115 Days with $0 amount.
* Industry wide material price increase on Item#14- 6" path, amount is $4,589.95 and 0 Days.
* Price escalation of payment on Item #13, 4.5 Sidewalk, amount is $5,504.28 and 0 Days.
* Price escalation of payment on Item #12, 10" H.E strength driveway, amount is $11,531.71 and 0 Days.
* Additional Days due to scope of work changes, added 311 Days.
* Several pay items at the beginning of the project that were changed-added quantities, amount is $114,503.14 and 0 Days.
* Final Cost Adjustment in the amount of $28,191.00 ...