Department: County Engineer
Department Head/Elected Official: Dr. Milton Rahman, PhD, P.E, PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): 21/0159
Vendor/Entity Legal Name (if applicable): Horizon International Group
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Horizon International Group in connection with George H. W. Bush Community Center, with a deduction in the amount of $21,797.07, Job No. 21/0159-6, UPIN 19104MF16U01, Precinct 3.
end
Background and Discussion:
George H. W. Bush Community Center is a complete renovation of 24,000 square feet of and A3 occupancy,
building to include offices, classrooms, lobby, multi-purpose rooms, ancillary spaces exterior cladding, and
MEP. All work shall be completed in accordance with all applicable codes and regulations, which will return the building to full operational use.
This change in contract includes a deduction to materials and labor cost.
Expected Impact:
This change allows unused funds to be returned to Harris County and allows the Contractor to be compensated with retention pending this court action.
Alternative Options:
Should we not move forward with this change order funds will not to be returned to Harris County and retention will not be released.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
_ Flooding
_ Environment
X Governance and Customer Service
Prior Court Action (if any):
Date
Agenda Item #
Action Taken
08/10/2021
374
Contract Award
06/14/2022
33
Change in Contract# 21/0159-1
07/19/2022
36
Change in Contract# 21/0159-2
08/23/2022
38
Change in Contract# 21/0159-3
10/18/2022
45
Change ...
Click here for full text