Legislation Details

File #: 24-2722    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 4/24/2024 In control: Commissioners Court
On agenda: 5/7/2024 Final action: 5/7/2024
Title: Request for approval of a change in contract with DT Construction, LP, in connection with Harris County Pollution Control Renovation - 2020, located at 101 S. Richey St., Suite H, Pasadena, TX 77506, adding 74 calendar days, with an addition in the amount of $119,871.64, Job No. 22/0283-1, UPIN 21272MF22601, Countywide, MWDBE Contracted Goal: 15.2%, MWDBE Current Participation: 15.2%.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): 22/0283
Vendor/Entity Legal Name (if applicable): DT Construction

MWDBE Contracted Goal (if applicable): 15.2%
MWDBE Current Participation (if applicable): 15.2%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with DT Construction, LP, in connection with Harris County Pollution Control Renovation - 2020, located at 101 S. Richey St., Suite H, Pasadena, TX 77506, adding 74 calendar days, with an addition in the amount of $119,871.64, Job No. 22/0283-1, UPIN 21272MF22601, Countywide, MWDBE Contracted Goal: 15.2%, MWDBE Current Participation: 15.2%.
end

Background and Discussion:
This project was approved on Commissioners Court on 10/13/2020. It provides interior renovation of existing Pollution Control Facilities in Pasadena. Improvements include upgrading of laboratory suite and facility to achieve 100% operational capacity during disaster events. It includes a full office suite renovation, emergency shower drains, water tank and new 1000KW emergency generator and water tank.

This change in contract provides adding general conditions, providing necessary materials, equipment and labor for additional electrical work for the generator shut down as well as additional safety bollards. This comes to a total of $119,871.64 and 74 days.


Expected Impact:
Upon completion of the project, Pollution Control will be able to maintain full operations during major disaster and storm events. Changes allow the completion of the project in accordance with the original intent of the project.

Alternative Options:
Delay the change order which would delay the completion of the project. Rebid or look at on-call vendors to pr...