Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 22/0013, UPIN 20101MF1KM01
Vendor/Entity Legal Name (if applicable): DVL Enterprises, LLC
MWDBE Contracted Goal (if applicable): 14%
MWDBE Current Participation (if applicable): 49.30%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with DVL Enterprises, LLC, in connection with final construction of Sidewalk and Bike Ln - Almeda Road (FM521) - 2020, with an addition in the amount of $144,430.69, Job No. 22/0013-2, UPIN 20101MF1KM01, Precinct 1, MWDBE Contracted Goal: 14%, MWDBE Current Participation: 49.30%.
end
Background and Discussion:
Project includes the construction of a sidewalk along Almeda Road between Old Spanish Trail and Holly Hall Street.
Change includes:
* New item for SWPPP Monthly Maintenance - protection of storm water runoff, reporting, etc. is a requirement of the project. Item was not included in the original bid items for the project. SWPPP Inspection and Maintenance - 5 months at $600/month - $3,000.00, 0 DAYS.
* Escalation rate adjustment for Item 22-Concrete Sidewalk (9") = $1,857.68, 0 days
* Escalation rate adjustment for Item 21-Curb Ramps (TY 20") = $114.87, 0 days
* Escalation rate adjustment for Item 20- Curb Ramps (TY 7) = $826.57, 0 days
* Escalation rate adjustment for Item 19- Curb Ramps (TY 5) = $981.32, 0 days
* Escalation rate adjustment for Item 18- Curb Ramps (TY 1) = $171.60, 0 days
* Escalation rate adjustment for Item 17-Concrete Sidewalk (8") = $20,714.04, 0 days
* Escalation rate adjustment for Item 16-Concrete Sidewalk (4.5") = $383.49, 0 days
* Escalation rate adjustment for Item 15-Concrete Driveways = $6,527.01, 0 days
* Final Cost Adjustment = $1...
Click here for full text