Legislation Details

File #: 24-2701    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 4/24/2024 In control: Commissioners Court
On agenda: 5/7/2024 Final action: 5/7/2024
Title: Request for approval of a change in contract with TB Concrete Construction in connection with final construction of W. Montgomery, TC Jester and W. Mount Houston Roads - 2018, adding 289 calendar days, with an addition in the amount of $88,810.49, Job No. 21/0106-2, UPIN 19101MF0Y201, Precincts 1 & 2, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
Sponsors: Mony Hossain
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No: 21/0106, UPIN 19101MF0Y201
Vendor/Entity Legal Name (if applicable): TB Concrete Construction

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with TB Concrete Construction in connection with final construction of W. Montgomery, TC Jester and W. Mount Houston Roads - 2018, adding 289 calendar days, with an addition in the amount of $88,810.49, Job No. 21/0106-2, UPIN 19101MF0Y201, Precincts 1 & 2, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
end
Background and Discussion:
Project includes construction of concrete sidewalks along West Mount Houston from Antoine Drive to West Montgomery Road, West Montgomery Road from Breen Drive to West Gulf Bank Road (City Limits) and TC Jester Boulevard from Star Peak Road to West Montgomery Road. Change includes a new item for heavy cleaning of storm sewer associated with an excessive amount of debris located within this section of existing storm sewer. Additional time is associated with delays caused by a conflict with an existing AT&T utility line and Exxon Delay.

Expected Impact:
Change allows the Contractor to be compensated for the additional work associated with removal of excessive amounts of debris.

Alternative Options:
Eliminate this section of storm sewer from the scope of work.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
x Transportation
_ Flooding
_ Environment
_ Governance and Customer Service

Prior Court Ac...

Click here for full text