Title: Request for approval of an agreement with HR Green, Inc., in the amount of $1,451,445, for engineering services to provide design, bidding, and construction phase engineering services in support of a stormwater detention basin along Jackson Bayou, HCFCD Unit R500-01-00. (Jackson Bayou Watershed, Bond ID F-107, Project ID R500-01-00-E001, Agreement No. 2022-130, Precinct 3, MWDBE Contracted Goal: 20%).
Attachments: 1. 050724 AGMT HR GREEN 2022-130 PCT 3 backup.pdf
Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): R500-01-00-E001
Vendor/Entity Legal Name (if applicable): HR Green, Inc.

MWDBE Contracted Goal (if applicable): 20%
MWDBE Current Participation (if applicable): 0%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of an agreement with HR Green, Inc., in the amount of $1,451,445, for engineering services to provide design, bidding, and construction phase engineering services in support of a stormwater detention basin along Jackson Bayou, HCFCD Unit R500-01-00. (Jackson Bayou Watershed, Bond ID F-107, Project ID R500-01-00-E001, Agreement No. 2022-130, Precinct 3, MWDBE Contracted Goal: 20%).
end

Background and Discussion:
This Agreement will provide the Jackson Bayou area with flood reduction benefits through engineering design of channel modifications on R500-01-00-E001 and a stormwater detention basin. The project has a prioritization score in the 2nd quartile under the 2022 Prioritization Framework approved by Commissioners Court.

Expected Impact:
During a 100-year flood event, it is estimated that 18 structures will no longer flood, 21 structures will have reduced flooding, and 66.8 acres and 1.5 roadway miles will be removed from the floodplain.

Alternative Options:
The alternative to approving this item would be to select a different consultant which could prevent the Flood Control District from meeting CDBG funding deadlines.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
X Flooding
X Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
02-08-2022
105.
ATN

Location:
Address (if applicable):
Precinct(s): Pre...

Click here for full text