Legislation Details

File #: 24-2636    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 4/23/2024 In control: Commissioners Court
On agenda: 5/7/2024 Final action: 5/7/2024
Title: Request for approval to execute an agreement with Transcend Engineers and Planners, LLC, in the amount of $93,183.00 for Professional Engineering Services to rebuild a traffic signal at the intersection of Beechnut Street and Beckford Drive, UPIN 24035MF35K01, Precinct 4, MWDBE Contracted Goal: 19.6%.
Sponsors: Mony Hossain
Attachments: 1. 24-2636-Consultant- UPIN 24035MF35K01-Transcend Engineers-Beechnut at Beckford-05.07.2024
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): UPIN 24035MF35K01
Vendor/Entity Legal Name (if applicable): Transcend Engineers and Planners, LLC.

MWDBE Contracted Goal (if applicable): 19.6%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with Transcend Engineers and Planners, LLC, in the amount of $93,183.00 for Professional Engineering Services to rebuild a traffic signal at the intersection of Beechnut Street and Beckford Drive, UPIN 24035MF35K01, Precinct 4, MWDBE Contracted Goal: 19.6%.
end

Background and Discussion:
Traffic signals are installed to improve the operations of an intersection and better facilitate pedestrian activities. As such, the consultant will be tasked with the signal design of the intersection and an evaluation of left turn lane storage to improve operations. The consultant will also be tasked with evaluating pedestrian accessibility through the provision of crosswalks and associated median nose opening adjustments required to facilitate pedestrian activities.

Expected Impact:
The installation of the new traffic signal should improve the operation of the intersection.

Alternative Options:
To not install the signal at the intersection, which will not offer the associated operational and pedestrian benefits.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
x Transportation
_ Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
12/19/2023
100
Authorization to Negotiate - Transcend Engineers and Planners, LLC.

Location: Beechnut Street and Beckford Drive
Address (if a...