Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No: 21/0109, UPIN 21289MF1Q001
Vendor/Entity Legal Name (if applicable): Reliance Construction Services, LP
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Reliance Construction Services, LP, in connection with final Water Distribution and Sanitary Sewer System Construction - East Lorino Street, adding 10 calendar days, with a deduction in the amount of $56,580.47 to reflect actual work completed, Job No. 21/0109-3, UPIN 21289MF1Q001, Precinct 1.
end
Background and Discussion:
Project consists of installing a water distribution system and sanitary sewer collection system to serve East Lorino Street in Precinct 1 of Harris County. The water distribution system includes the installation of a waterline along East Lorino Street, water service connections to existing residences and the decommissioning of existing wells. The sanitary sewer system includes installation of sanitary sewer line along East Lorino Street, sanitary manholes, service connections to existing residences, and abandonment of on-site sewage facilities.
Expected Impact:
Change allows for the completion of the project as designed and per the contract documents.
Alternative Options:
Deduct scope items to allow for work to be completed in original contract time.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
x Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date
Agenda Item #
Action Taken
08/10/2021
366
Contract Award
06/28/2022
36
Contra...