Legislation Details

File #: 24-1880    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 3/18/2024 In control: Commissioners Court
On agenda: 3/26/2024 Final action: 3/26/2024
Title: Request for approval of an award on the basis of only bid to First Class Units Inc in the amount of $489,480 for construction of four monuments within the Channelview and Northshore Community for Precinct 2, and for the County Clerk to execute any applicable bonds to be received (240014), MWDBE Contracted Goal: 17%.
Attachments: 1. 24-1880 Award- First Class Units Inc
Department: Purchasing
Department Head/Elected Official: DeWight Dopslauf

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): 240014
Vendor/Entity Legal Name (if applicable): First Class Units Inc

MWDBE Contracted Goal (if applicable): 17%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of an award on the basis of only bid to First Class Units Inc in the amount of $489,480 for construction of four monuments within the Channelview and Northshore Community for Precinct 2, and for the County Clerk to execute any applicable bonds to be received (240014), MWDBE Contracted Goal: 17%.
end

Background and Discussion:
The Community Monuments Project aims to construct two architectural landmarks in Northshore and two in Channelview. Both communities actively engaged in a collaborative outreach process to choose the designs for these monuments.

Expected Impact:
Constructing four monuments in Channelview and Northshore will serve as landmarks of community pride and identity, fostering a sense of belonging among residents. These monuments will not only enhance the aesthetic appeal of the areas but also attract visitors, potentially boosting local tourism and economic activity. By improving the visibility and recognition of these neighborhoods, the monuments can lead to increased investment and development opportunities, ultimately improving the overall quality of life for residents.

Alternative Options:
Court may elect to not award the low bidder, and HCED can explore additional options, however this will cause project delays.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
01/30/20...