Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Transmittal
Project ID (if applicable): Job No. 21/0444
Vendor/Entity Legal Name (if applicable): Jerdon Enterprise, LP
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Transmittal by the Office of the County Engineer of a substantial completion certificate with Jerdon Enterprise LP, for improvements in connection with Addicks Clodine Road - Pedestrian Undercrossing - 2019, Job No. 21/0444, UPIN 20103N302903, Precinct 4.
end
Background and Discussion:
The Substantial Completion Certificate provides documentation that a capital improvement project meets the qualifications of Substantial Completion in accordance with the Contract Documents as determined by the County Engineer. Substantial Completion establishes the date on which a capital improvement enters service as a Harris County asset. The establishment and reporting of this date is important for all governmental entities as outlined in the GASB Statement #34, Capital Assets & Depreciation Guidance, August 31, 2001. These certificates provide a method by which Harris County may document and record this date.
Expected Impact:
This action establishes the date on which a capital improvement enters service as a Harris County asset.
Alternative Options:
No alternative option.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
X Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date
Agenda Item #
Action Taken
10/11/2022
253
Contract Award
08/29/2023
78
Contract Amendment for additional funds and extension of project term
Location:
Address (if applicable):
Pre...
Click here for full text