Title: Request for approval of an amendment to an agreement with R.R.P. Consulting Engineers, L.L.C., formerly S&B Infrastructure, LTD, in the amount of $100,000, to provide additional construction phase engineering services for the Little York Stormwater Detention Basin. (Halls Bayou Watershed, Bond ID C-35, Project ID P518-10-00-E001, Agreement No. 2022-69, Precinct 2, Justification for 0% MWDBE Participation Goal: 0% - Non-Divisible).
Attachments: 1. 032624 AGMT RRP 2022-69 PCT 2 backup.pdf
Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): P518-10-00-E001
Vendor/Entity Legal Name (if applicable): R.R.P. Consulting Engineers, L.L.C. formerly S&B Infrastructure, LTD

MWDBE Contracted Goal (if applicable): 0%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: 0% - Non-Divisible

Request Summary (Agenda Caption):
title
Request for approval of an amendment to an agreement with R.R.P. Consulting Engineers, L.L.C., formerly S&B Infrastructure, LTD, in the amount of $100,000, to provide additional construction phase engineering services for the Little York Stormwater Detention Basin. (Halls Bayou Watershed, Bond ID C-35, Project ID P518-10-00-E001, Agreement No. 2022-69, Precinct 2, Justification for 0% MWDBE Participation Goal: 0% - Non-Divisible).
end

Background and Discussion:
The P518-10-00-E001 (Phase 2) project is in northeast Houston in Harris County Precinct 2. The purpose of the project is to implement channel conveyance improvements (desilting, slope stabilization, crossing replacements, culvert repair) along P118-14-00 between the Hopper and Little York stormwater detention basins installed during the P518-10-00-E002 (Phase 1) project. Phase 2 will be constructed using the remaining CDBG-DR 2017 Hurricane Harvey Round 1 grant funds remaining from Phase 1.

The prior agreement included the funding to carry the engineer of record through design phase services. Additional funding is needed so the engineer of record and complete the bidding and construction phase services.

Expected Impact:
This project seeks to reduce flood risks and strengthen resiliency in Harris County by alleviating property and structural damages to the adjacent community. The objective is to restore channel capacity and increase conveyance of storm wat...